Creek Beach - Summer is a project by Dubai Creek Harbour L.L.C, recorded at 100% complete at its last Dubai Land Department inspection. 10 sales registered in the trailing 12 months at a median AED 1.72M (1 981 AED per square foot). Registry facts come from DLD; prices are registered transactions, not asking prices.

## Registry record

| Field | Value | Provenance |
|---|---|---|
| Developer | Dubai Creek Harbour L.L.C | DLD verified |
| Status | Finished | DLD verified |
| Construction progress | 100% | DLD verified |
| Registered with DLD | 4 Apr 2019 | DLD verified |
| Construction started | 15 Aug 2019 | DLD verified |
| Declared completion | 7 Mar 2023 | DLD verified |
| Units in the project | 305 | DLD verified |
| Project area | 336 532 sqm | DLD verified |
| Escrow agent | Mashreq Bank Psc | DLD verified |
| Project number | 2150 | DLD verified |

## Latest registered sales

| Date | Property | Registration | Size sqft | Price AED | AED/sqft |
|---|---|---|---|---|---|
| 2026-11-17 | 2 B/R Flat — Summer at Creek Beach Building 3 | Ready | 1 103 | 2 000 000 | 1 814 |
| 2026-10-26 | 2 B/R Flat — Summer at Creek Beach Building 3 | Ready | 998 | 2 000 000 | 2 004 |
| 2026-09-09 | 1 B/R Flat — Summer at Creek Beach Building 2 | Ready | 943 | 1 720 000 | 1 823 |
| 2026-08-18 | 2 B/R Flat — Summer at Creek Beach Building 2 | Ready | 1 335 | 2 400 000 | 1 798 |
| 2026-06-25 | 1 B/R Flat — Summer at Creek Beach Building 2 | Ready | 332 | 650 000 | 1 957 |
| 2026-04-02 | 1 B/R Flat — Summer at Creek Beach Building 1 | Ready | 669 | 1 670 000 | 2 497 |
| 2026-02-27 | 1 B/R Flat — Summer at Creek Beach Building 1 | Ready | 668 | 1 580 000 | 2 365 |
| 2026-02-12 | 1 B/R Flat — Summer at Creek Beach Building 1 | Ready | 669 | 1 500 000 | 2 242 |
| 2026-02-10 | 1 B/R Flat — Summer at Creek Beach Building 4 | Ready | 716 | 1 740 000 | 2 429 |
| 2025-12-15 | 1 B/R Flat — Summer at Creek Beach Building 2 | Ready | 978 | 1 725 000 | 1 764 |

| Measure | Value | Year on year |
|---|---|---|
| Median sale price | AED 1.72M | +4.4% |
| Interquartile range | AED 1.60M – AED 1.94M | |
| Median price per sqft | 1 981 AED | -8.9% |
| Registered sales, 12 months | 10 | -37.5% |
| Off-plan share | 0.0% | |

## By number of bedrooms

| Homes | Sales | Median price | Median AED/sqft | Median size | Median rent | Gross yield |
|---|---|---|---|---|---|---|
| 1-bedroom apartments | 7 | AED 1.67M | 2 242 | 669 sqft | — | — |
| 2-bedroom apartments | 2 | — | — | — | — | — |
| 3-bedroom apartments | 1 | — | — | — | — | — |

## Buildings in this project

| Building (DLD name) | Sales | Median price | Median AED/sqft | Off-plan |
|---|---|---|---|---|
| Summer At Creek Beach Building 2 | 4 | — | — | 0.0% |
| Summer At Creek Beach Building 1 | 3 | — | — | 0.0% |
| Summer At Creek Beach Building 3 | 2 | — | — | 0.0% |
| Summer At Creek Beach Building 4 | 1 | — | — | 0.0% |
| Lotus At Creek Beach Building 3 | 0 | — | — | None% |
| Savanna At Creek Beach Building 3 | 0 | — | — | None% |
| Mangrove At Creek Beach Building 1 | 0 | — | — | None% |
| Creek Beach - Canopy Building 5 | 0 | — | — | None% |
| Breeze At Creek Beach Building 1 | 0 | — | — | None% |
| Bayshore At Creek Beach Building 1 | 0 | — | — | None% |
| Orchid At Creek Beach Building 2 | 0 | — | — | None% |
| Lotus At Creek Beach Building 4 | 0 | — | — | None% |
| Savanna At Creek Beach Building 2 | 0 | — | — | None% |
| Cedar At Creek Beach Building 2 | 0 | — | — | None% |
| Creek Beach - Canopy Building 3 | 0 | — | — | None% |
| Creek Beach - Moor Building 3 | 0 | — | — | None% |
| Surf At Creek Beach Building 1 | 0 | — | — | None% |
| Vida Residences At Creek Beach | 0 | — | — | None% |
| Rosewater At Creek Beach Building 2 | 0 | — | — | None% |
| Creek Beach - Moor Building 1 | 0 | — | — | None% |
| Sunset At Creek Beach Building 3 | 0 | — | — | None% |
| Breeze At Creek Beach Building 3 | 0 | — | — | None% |
| Sunset At Creek Beach Building 2 | 0 | — | — | None% |
| Bayshore At Creek Beach Building 3 | 0 | — | — | None% |
| Grove At Creek Beach Building 1 | 0 | — | — | None% |
| Grove At Creek Beach Building 2 | 0 | — | — | None% |
| Cedar At Creek Beach Building 1 | 0 | — | — | None% |
| Creek Beach - Moor Building 2 | 0 | — | — | None% |
| Grove At Creek Beach Building 3 | 0 | — | — | None% |
| Lotus At Creek Beach Building 1 | 0 | — | — | None% |
| Mangrove At Creek Beach Building 2 | 0 | — | — | None% |
| Cedar At Creek Beach Building 4 | 0 | — | — | None% |
| Creek Beach - Moor Building 4 | 0 | — | — | None% |
| Rosewater At Creek Beach Building 1 | 0 | — | — | None% |
| Savanna At Creek Beach Building 1 | 0 | — | — | None% |
| Creek Beach - Canopy Building 1 | 0 | — | — | None% |
| Breeze At Creek Beach Building 2 | 0 | — | — | None% |
| Sunset At Creek Beach Building 1 | 0 | — | — | None% |
| Bayshore At Creek Beach Building 2 | 0 | — | — | None% |
| Bayshore At Creek Beach Building 4 | 0 | — | — | None% |
| Grove At Creek Beach Building 5 | 0 | — | — | None% |
| Orchid At Creek Beach Building 1 | 0 | — | — | None% |
| Lotus At Creek Beach Building 2 | 0 | — | — | None% |
| Cedar At Creek Beach Building 3 | 0 | — | — | None% |
| Creek Beach - Canopy Building 2 | 0 | — | — | None% |
| Creek Beach - Canopy Building 4 | 0 | — | — | None% |
| Surf At Creek Beach Building 2 | 0 | — | — | None% |
| Vida Hotel At Creek Beach | 0 | — | — | None% |
| Rosewater At Creek Beach Building 3 | 0 | — | — | None% |
| Grove At Creek Beach Building 4 | 0 | — | — | None% |

## Price per square foot by month

| Month | Sales | Median AED/sqft | IQR |
|---|---|---|---|
| Oct 2024 | 8 | 2 113 | 2 007 – 2 209 |
| Sep 2024 | 4 | insufficient data | |
| Aug 2024 | 3 | insufficient data | |
| Jul 2024 | 6 | 1 807 | 1 633 – 2 052 |
| Jun 2024 | 3 | insufficient data | |
| May 2024 | 5 | 1 685 | 1 544 – 1 873 |
| Apr 2024 | 1 | insufficient data | |
| Mar 2024 | 2 | insufficient data | |
| Feb 2024 | 11 | 2 103 | 1 955 – 2 195 |
| Jan 2024 | 9 | 1 821 | 1 712 – 1 904 |
| Dec 2023 | 9 | 2 023 | 1 809 – 2 045 |
| Nov 2023 | 6 | 1 849 | 1 818 – 1 893 |
| Oct 2023 | 12 | 1 936 | 1 880 – 1 981 |

## What these numbers do not show

- Prices from the developer. Nothing here is a price list, a payment plan or availability — these are transactions already registered with DLD.
- Whether construction is moving. The completion percentage is the figure recorded at the last technical inspection, and inspections are irregular: an unchanged number does not mean work stopped.
- A handover promise. The declared completion date is a registry field, not a commitment.
- A reliable price. Only 10 sales registered in the last 12 months here.
- Asking prices. Everything here is a registered transaction; what a home was listed at is a different number.
- Off-market and cash-equivalent deals that never reach the registry, and the price actually negotiated before registration.
- Service charges, chiller fees, agency commission, DLD transfer fees or mortgage costs — none of them are inside these prices.

## Questions and answers

**Who is the developer of Creek Beach - Summer?**

The Dubai Land Department project registry lists Dubai Creek Harbour L.L.C as the developer of Creek Beach - Summer.

**Is Creek Beach - Summer completed?**

The DLD registry status of Creek Beach - Summer is Finished, 100% complete at the last DLD inspection. The declared completion date in the registry is 7 Mar 2023 — a registry date, not a handover promise.

**How many homes are in Creek Beach - Summer?**

The DLD registry records 305 units in Creek Beach - Summer.

**What is the price per square foot in Creek Beach - Summer?**

Over the last 12 complete months the median registered sale in Creek Beach - Summer was AED 1.72M, or AED 1 981 per sqft, from 10 registered sales. These are DLD registrations, not asking prices.

**Who holds the escrow account for Creek Beach - Summer?**

The escrow agent recorded by DLD for Creek Beach - Summer is Mashreq Bank Psc.

**Where is Creek Beach - Summer?**

Creek Beach - Summer is in the Dubai Creek Harbour community.

**Where does this data come from?**

From Dubai Land Department open data — the project registry, unit register and registered sales — rebuilt every night. Data through 24 Nov 2026.

---

**Source:** Dubai Land Department open data, compiled by Continental Club Property  
**Data through:** 24 Nov 2026  
**Methodology:** https://datadubai.ae/methodology/ (v1.0)  
**License:** Reuse permitted with attribution  
**Canonical:** https://datadubai.ae/projects/creek-beach-summer/  
**Suggested citation:** Continental Club Property, "Creek Beach - Summer", Data Dubai, data through 24 Nov 2026, https://datadubai.ae/projects/creek-beach-summer/  
**Disclaimer:** Registered transactions, not asking prices. Not investment advice, not a valuation. Not affiliated with or endorsed by the Dubai Land Department.