# La Tilia At Villanova Phase 1

La Tilia At Villanova Phase 1 is a project by North Dubailand Projects L.L.C, recorded at 14% complete at its last Dubai Land Department inspection. 59 sales registered in the trailing 12 months at a median AED 3.19M (1 445 AED per square foot). Registry facts come from DLD; prices are registered transactions, not asking prices.

## Registry record

| Field | Value | Provenance |
|---|---|---|
| Developer | North Dubailand Projects L.L.C | DLD verified |
| Status | Active | DLD verified |
| Construction progress | 14% | DLD verified |
| Registered with DLD | 23 Dec 2024 | DLD verified |
| Construction started | 21 Jan 2025 | DLD verified |
| Declared completion | 21 Aug 2028 | DLD verified |
| Units in the project | 410 | DLD verified |
| Project area | 95 049 sqm | DLD verified |
| Escrow agent | First Abu Dhabi Bank P.J.S.C. | DLD verified |
| Project number | 3455 | DLD verified |

La Tilia At Villanova Phase 1 is a project by North Dubailand Projects L.L.C, recorded at 14% complete at its last Dubai Land Department inspection. 59 sales registered in the trailing 12 months at a median AED 3.19M (1 445 AED per square foot). Registry facts come from DLD; prices are registered transactions, not asking prices.

| Measure | Value | Year on year |
|---|---|---|
| Median sale price | AED 3.19M | +0.2% |
| Interquartile range | AED 3.07M – AED 3.55M | |
| Median price per sqft | 1 445 AED | +2.1% |
| Registered sales, 12 months | 59 | -84.9% |
| Off-plan share | 100.0% | |

## By number of bedrooms

| Homes | Sales | Median price | Median AED/sqft | Median size | Median rent | Gross yield |
|---|---|---|---|---|---|---|
| 3-bedroom apartments | 32 | AED 3.07M | 1 597 | 1 884 sqft | — | — |
| 4-bedroom apartments | 27 | AED 3.56M | 1 196 | 3 036 sqft | — | — |

## Price per square foot by month

| Month | Sales | Median AED/sqft | IQR |
|---|---|---|---|
| Sep 2026 | 7 | 1 247 | 1 174 – 1 386 |
| Aug 2026 | 2 | insufficient data | |
| Jul 2026 | 1 | insufficient data | |
| Jun 2026 | 3 | insufficient data | |
| May 2026 | 3 | insufficient data | |
| Apr 2026 | 4 | insufficient data | |
| Mar 2026 | 2 | insufficient data | |
| Feb 2026 | 9 | 1 481 | 1 251 – 1 627 |
| Jan 2026 | 20 | 1 592 | 1 204 – 1 640 |
| Dec 2025 | 3 | insufficient data | |
| Nov 2025 | 2 | insufficient data | |
| Oct 2025 | 3 | insufficient data | |
| Sep 2025 | 0 | insufficient data | |

## What these numbers do not show

- Prices from the developer. Nothing here is a price list, a payment plan or availability — these are transactions already registered with DLD.
- Whether construction is moving. The completion percentage is the figure recorded at the last technical inspection, and inspections are irregular: an unchanged number does not mean work stopped.
- A handover promise. The declared completion date is a registry field, not a commitment.
- Asking prices. Everything here is a registered transaction; what a home was listed at is a different number.
- Off-market and cash-equivalent deals that never reach the registry, and the price actually negotiated before registration.
- Service charges, chiller fees, agency commission, DLD transfer fees or mortgage costs — none of them are inside these prices.

---

**Source:** Dubai Land Department open data, compiled by Continental Club Property  
**Data through:** 22 Oct 2026  
**Methodology:** https://datadubai.ae/methodology/ (v1.0)  
**License:** Reuse permitted with attribution  
**Canonical:** https://datadubai.ae/projects/la-tilia-at-villanova-phase-1/  
**Suggested citation:** Continental Club Property, "La Tilia At Villanova Phase 1", Dubai Data, data through 22 Oct 2026, https://datadubai.ae/projects/la-tilia-at-villanova-phase-1/  
**Disclaimer:** Registered transactions, not asking prices. Not investment advice, not a valuation. Not affiliated with or endorsed by the Dubai Land Department.