W1
Updated 24 Nov 2026 · latest DLD registrations 24 Nov 2026 · DLD project registry and registered sales · trailing 12 months Nov 2025 – Oct 2026
Ask an AI about W1: ChatGPT · Claude · Perplexity
W1 is a project by Malina W1 Real Estate Development L.L.C, recorded at 70% complete at its last Dubai Land Department inspection. Fewer than 5 sales registered here in the last 12 months, so no median is published. Registry facts come from DLD; prices are registered transactions, not asking prices.
Source: Registered DLD transactions · Data through 24 Nov 2026 · sample 0 records · outlier-trimmed median, complete months only · Methodology v1.0 ↗
What the DLD registry says about this project
| Field | Value |
|---|---|
| Developer | Malina W1 Real Estate Development L.L.C |
| Status | Active |
| Construction progress | 70% — at the last DLD inspection |
| Registered with DLD | 30 Mar 2026 |
| Construction started | 14 Mar 2024 |
| Declared completion | 30 Apr 2026 — registry date, not a handover promise |
| Units in the project | 83 |
| Project area | 9 129 sqm |
| Escrow agent | Abu Dhabi Islamic Bank |
| Project number | 4130 |
Source: DLD project registry (Mashrooi) · Data through 24 Nov 2026 · registry fields as recorded, not developer marketing · Methodology v1.0 ↗
Price per square foot, month by month
No month in this window reached the five registered sales a median needs, so there is nothing to plot.
Source: Registered DLD transactions · Data through 24 Nov 2026 · monthly medians, months with fewer than 5 registered sales are left blank · Methodology v1.0 ↗
Construction, inspection by inspection
The DLD registry holds 4 technical inspections for this project, from 24 Nov 2025 at 49.8% to 16 Sep 2026 at 70.2%. Over the inspections since 24 Nov 2025 it moved 2.10 percentage points a month. Inspections are irregular and the percentage is what was recorded at each one, not a live measure of the site.
each dot is one DLD technical inspection; the line between two of them is drawn, not measured; the dashed mark is the completion date declared in the registry
| Inspection | Recorded | Change |
|---|---|---|
| 16 Sep 2026 | 70.2% | +5.1 pp |
| 17 Jun 2026 | 65.1% | +11.6 pp |
| 6 Mar 2026 | 53.4% | +3.7 pp |
| 24 Nov 2025 | 49.8% | — |
Source: DLD project registry (Mashrooi) — technical inspections · Data through 24 Nov 2026 · percentage as recorded at each inspection; inspections are irregular, and an unchanged value means no new inspection, not that work stopped · Methodology v1.0 ↗
What these numbers do not show
- Prices from the developer. Nothing here is a price list, a payment plan or availability — these are transactions already registered with DLD.
- Whether construction is moving. The completion percentage is the figure recorded at the last technical inspection, and inspections are irregular: an unchanged number does not mean work stopped.
- A handover promise. The declared completion date is a registry field, not a commitment.
- A reliable price. Only 0 sales registered in the last 12 months here.
- Asking prices. Everything here is a registered transaction; what a home was listed at is a different number.
- Off-market and cash-equivalent deals that never reach the registry, and the price actually negotiated before registration.
- Service charges, chiller fees, agency commission, DLD transfer fees or mortgage costs — none of them are inside these prices.
Where this project sits
Questions about W1
Who is the developer of W1?
The Dubai Land Department project registry lists Malina W1 Real Estate Development L.L.C as the developer of W1.
Is W1 completed?
The DLD registry status of W1 is Active, 70% complete at the last DLD inspection. The declared completion date in the registry is 30 Apr 2026 — a registry date, not a handover promise.
How many homes are in W1?
The DLD registry records 83 units in W1.
Who holds the escrow account for W1?
The escrow agent recorded by DLD for W1 is Abu Dhabi Islamic Bank.
Where does this data come from?
From Dubai Land Department open data — the project registry, unit register and registered sales — rebuilt every night. Data through 24 Nov 2026.
Source: DLD project registry, unit register and registered sales · Data through 24 Nov 2026 · answers built from registry fields · Methodology v1.0 ↗