Construction progress
Data through 22 Oct 2026 · DLD inspections · trailing 12 months Oct 2025 – Sep 2026 · rebuilt daily
Dubai projects grouped by the completion percentage recorded at their last Dubai Land Department technical inspection. The percentage is measured, not estimated, but the measurements are irregular — treat each band as the state at the last inspection.
Projects by completion band
| Band | Projects | Units |
|---|---|---|
| 0-20% complete | 1 411 | 315 500 |
| 20-40% complete | 276 | 80 967 |
| 40-60% complete | 197 | 53 422 |
| 60-80% complete | 173 | 41 409 |
| 80-100% complete | 1 807 | 480 999 |
Source: Registered DLD transactions · Data through 22 Oct 2026 · percentage recorded at the last DLD technical inspection · Methodology v1.0 ↗
What these numbers do not show
- Live site progress; inspections are irregular.
- Projects with no inspection record in the registry.