Topaz Residences 1Finished100% built136 homesDLD data through 24 Nov 2026

Updated 24 Nov 2026 · latest DLD registrations 24 Nov 2026 · DLD project registry and registered sales · trailing 12 months Nov 2025 – Oct 2026

Ask an AI about Topaz Residences 1: ChatGPT · Claude · Perplexity

Topaz Residences 1 is a project by Gulf General Investments Co. (P.S.C), recorded at 100% complete at its last Dubai Land Department inspection. 5 sales registered in the trailing 12 months at a median AED 725k (956 AED per square foot). Registry facts come from DLD; prices are registered transactions, not asking prices.

Median sale price
AED 725k +13.7% y/y
≈ US$ 197k · typical range AED 715k – AED 730k
DLD verified
Median price per sqft
AED 956/sqft +5.8% y/y
typical range 953 – 1 024 AED/sqft
DLD verified
Registered sales
5 -68.8% y/y
all property types · trailing 12 complete months
DLD verified
Off-plan share
0.0%
of registered sales in the window
DLD verified

Source: Registered DLD transactions · Data through 24 Nov 2026 · sample 5 records · outlier-trimmed median, complete months only · Methodology v1.0 ↗

What the DLD registry says about this project

FieldValue
DeveloperGulf General Investments Co. (P.S.C)
StatusFinished
Construction progress100% — at the last DLD inspection
Registered with DLD25 Feb 2015
Construction started5 Jun 2014
Declared completion13 Dec 2018 — registry date, not a handover promise
Units in the project136
Project area9 482 sqm
Escrow agentDubai Islamic Bank (Public Joint Stock Company)
Project number1635

Source: DLD project registry (Mashrooi) · Data through 24 Nov 2026 · registry fields as recorded, not developer marketing · Methodology v1.0 ↗

Price per square foot, month by month

No month in this window reached the five registered sales a median needs, so there is nothing to plot.

Source: Registered DLD transactions · Data through 24 Nov 2026 · monthly medians, months with fewer than 5 registered sales are left blank · Methodology v1.0 ↗

Construction, inspection by inspection

The DLD registry holds 7 technical inspections for this project, from 16 Sep 2015 at 23.8% to 13 Dec 2018 at 100.0%. The last inspection recorded it complete. Inspections are irregular and the percentage is what was recorded at each one, not a live measure of the site.

0%25%50%75%100%declared 2018-12-132015-09-162018-12-13

each dot is one DLD technical inspection; the line between two of them is drawn, not measured; the dashed mark is the completion date declared in the registry

InspectionRecordedChange
13 Dec 2018100.0% +9.7 pp
14 Mar 201890.3% +10.2 pp
11 Oct 201780.1% +12.8 pp
23 Feb 201767.2% +12.1 pp
5 Oct 201655.2% +17.1 pp
10 Feb 201638.0% +14.2 pp
16 Sep 201523.8% —

Source: DLD project registry (Mashrooi) — technical inspections · Data through 24 Nov 2026 · percentage as recorded at each inspection; inspections are irregular, and an unchanged value means no new inspection, not that work stopped · Methodology v1.0 ↗

By number of bedrooms

HomesSalesMedian priceMedian AED/sqftMedian sizeMedian rentGross yield
1-bedroom apartments low sample (5) 5AED 725k 956 764 sqft — —

Source: Registered DLD sales and Ejari rental contracts · Data through 24 Nov 2026 · yield shown only where at least 15 rents and 15 ready-home sales support it · Methodology v1.0 ↗

Latest registered sales

DatePropertyRegistrationSizePriceAED/sqft
24 Jul 20261 B/R FlatReady 656 sqftAED 715 000 1 089
9 Jul 20261 B/R FlatReady 693 sqftAED 710 000 1 024
2 Jul 20261 B/R FlatReady 813 sqftAED 725 000 892
9 Feb 20261 B/R FlatReady 850 sqftAED 810 000 953
18 Dec 20251 B/R FlatReady 764 sqftAED 730 000 956

Source: Registered DLD transactions · Data through 24 Nov 2026 · individual registrations, shown exactly as recorded, without trimming · Methodology v1.0 ↗

Every registration, on request

The full DLD record for Topaz Residences 1: every registered sale, mortgage and gift, and every Ejari rent contract. It loads only when you ask; filter, sort and download it as CSV.

Registered sales by year

02550752015201620172018201920202021202220232024202520260255075201620182020202220242026

registered sales per calendar year; the current year is incomplete

By month

0123NovDecJanFebMarAprMayJunJulAugSepOct0123DecFebAprJunAugOct

registered sales per month, Nov 2025 – Oct 2026

YearSalesMedian priceMedian AED/sqftTotal registered value
20264— —AED 2.96M
202512AED 672k 903AED 7.97M
202420AED 588k 768AED 11.71M
202318AED 495k 686AED 8.94M
202210AED 455k 641AED 4.62M
20215AED 460k 597AED 2.20M
202012AED 501k 712AED 6.12M
201910AED 560k 745AED 5.96M
20181— —AED 666k
201723AED 669k 891AED 15.11M
201682AED 672k 903AED 55.06M
201531AED 690k 908AED 21.40M

Source: Registered DLD transactions · Data through 24 Nov 2026 · calendar years; the current year is partial · Methodology v1.0 ↗

Rent and gross yield by year, 2019–2026

40k50k60k2019202020212022202320242025202640k50k60k2019202120232025

1-bed flat: median annual rent, AED, of new and renewed Ejari contracts by start year; band = middle half of contracts

Median annual rent, AED thousand
Year1-bed flatGross yield
2026 YTD 58k—
2025 56k—
2024 50k8.51%
2023 43k8.69%
2022 38k—
2021 36k—
2020 40k—
2019 46k—

Source: Ejari rental contracts and registered DLD sales · Data through 24 Nov 2026 · median annual rent per year a contract starts, shown from 15 contracts; yield = median rent ÷ median ready-home price of the same year and home type, from 15 of each · Methodology v1.0 ↗

What these numbers do not show

  • Prices from the developer. Nothing here is a price list, a payment plan or availability — these are transactions already registered with DLD.
  • Whether construction is moving. The completion percentage is the figure recorded at the last technical inspection, and inspections are irregular: an unchanged number does not mean work stopped.
  • A handover promise. The declared completion date is a registry field, not a commitment.
  • A reliable price. Only 5 sales registered in the last 12 months here.
  • Asking prices. Everything here is a registered transaction; what a home was listed at is a different number.
  • Off-market and cash-equivalent deals that never reach the registry, and the price actually negotiated before registration.
  • Service charges, chiller fees, agency commission, DLD transfer fees or mortgage costs — none of them are inside these prices.

Nearby projects

10 projects with a page on this site are registered within 1.2 km of Topaz Residences 1. Distance is measured between the coordinates in the DLD project registry.

ProjectDistanceBuiltUnits
Axis Residences 3
Finished · Gulf General Investments Co. (P.S.C)
58 m100%128
Axis Residences 4
Finished · Gulf General Investments Co. (P.S.C)
59 m100%128
Topaz Residences 2
Finished · Gulf General Investments Co. (P.S.C)
138 m100%202
Axis Residences 2
Finished · Gulf General Investments Co. (P.S.C)
226 m100%284
Axis Residences 1
Finished · Gulf General Investments Co. (P.S.C)
234 m100%316
Platinum Residence 2
Finished · Gulf General Investments Co. (P.S.C)
384 m100%80
Binghatti Apartments
Finished · Binghatti Developers Fze
451 m100%224
Axis Residences 5
Finished · Gulf General Investments Co. (P.S.C)
477 m100%112
Topaz Residences 3
Finished · Gulf General Investments Co. (P.S.C)
601 m100%112
Arabian Gate
Finished · Time Properties
632 m100%716

The map loads only when you ask for it (OpenStreetMap, no tracking).

Source: DLD project registry coordinates · Data through 24 Nov 2026 · map © OpenStreetMap contributors · Methodology v1.0 ↗

Where this project sits

More projects in Silicon Oasis

Questions about Topaz Residences 1

Who is the developer of Topaz Residences 1?

The Dubai Land Department project registry lists Gulf General Investments Co. (P.S.C) as the developer of Topaz Residences 1.

Is Topaz Residences 1 completed?

The DLD registry status of Topaz Residences 1 is Finished, 100% complete at the last DLD inspection. The declared completion date in the registry is 13 Dec 2018 — a registry date, not a handover promise.

How many homes are in Topaz Residences 1?

The DLD registry records 136 units in Topaz Residences 1.

What is the price per square foot in Topaz Residences 1?

Over the last 12 complete months the median registered sale in Topaz Residences 1 was AED 725k, or AED 956 per sqft, from 5 registered sales. These are DLD registrations, not asking prices.

Who holds the escrow account for Topaz Residences 1?

The escrow agent recorded by DLD for Topaz Residences 1 is Dubai Islamic Bank (Public Joint Stock Company).

Where is Topaz Residences 1?

Topaz Residences 1 is in the Silicon Oasis community. 10 other projects with a page on this site are registered within 1.2 km; the closest is Axis Residences 3, about 58 m away.

Where does this data come from?

From Dubai Land Department open data — the project registry, unit register and registered sales — rebuilt every night. Data through 24 Nov 2026.

Source: DLD project registry, unit register and registered sales · Data through 24 Nov 2026 · answers built from registry fields · Methodology v1.0 ↗

Cite or reuse this data

Machine-readable mirrors of this page: Markdown · JSON · llms.txt. How to cite: “Topaz Residences 1 — Data Dubai, Continental Club Property, data through 24 Nov 2026, https://datadubai.ae/projects/topaz-residences-1/”. Reuse is permitted with attribution.