Data Dubai

Binghatti Gate

Binghatti GateFinished100% built132 homesDLD data through 24 Nov 2026

Updated 24 Nov 2026 · latest DLD registrations 24 Nov 2026 · DLD project registry and registered sales · trailing 12 months Nov 2025 – Oct 2026

Ask an AI about Binghatti Gate: ChatGPT · Claude · Perplexity

Binghatti Gate is a project by Binghatti Developers Fze, recorded at 100% complete at its last Dubai Land Department inspection. 12 sales registered in the trailing 12 months at a median AED 929k (1 043 AED per square foot). Registry facts come from DLD; prices are registered transactions, not asking prices.

Median sale price
AED 929k +24.3% y/y
≈ US$ 253k · typical range AED 749k – AED 1.04M
DLD verified
Median price per sqft
AED 1 043/sqft -5.5% y/y
typical range 882 – 1 154 AED/sqft
DLD verified
Registered sales
12 -40.0% y/y
all property types · trailing 12 complete months
DLD verified
Off-plan share
0.0%
of registered sales in the window
DLD verified

Source: Registered DLD transactions · Data through 24 Nov 2026 · sample 12 records · outlier-trimmed median, complete months only · Methodology v1.0 ↗

What the DLD registry says about this project

FieldValue
DeveloperBinghatti Developers Fze
StatusFinished
Construction progress100% — at the last DLD inspection
Registered with DLD1 Mar 2021
Construction started1 Nov 2020
Declared completion17 Jan 2022 — registry date, not a handover promise
Units in the project132
Project area10 531 sqm
Escrow agentSharjah Islamic Bank
Project number2232

Source: DLD project registry (Mashrooi) · Data through 24 Nov 2026 · registry fields as recorded, not developer marketing · Methodology v1.0 ↗

Price per square foot, month by month

Fewer than six months reached the five registered sales a median needs — too few to draw a line that would mean anything.

Source: Registered DLD transactions · Data through 24 Nov 2026 · monthly medians, months with fewer than 5 registered sales are left blank; the line stops at Jul 2024: in the 27 months since, no month reached the five registered sales a median needs (36 in total) · Methodology v1.0 ↗

Construction, inspection by inspection

The DLD registry holds 3 technical inspections for this project, from 21 Feb 2021 at 35.1% to 17 Jan 2022 at 100.0%. The last inspection recorded it complete. Inspections are irregular and the percentage is what was recorded at each one, not a live measure of the site.

0%25%50%75%100%declared 2022-01-172021-02-212022-01-17

each dot is one DLD technical inspection; the line between two of them is drawn, not measured; the dashed mark is the completion date declared in the registry

InspectionRecordedChange
17 Jan 2022100.0% +39.9 pp
23 May 202160.1% +25.0 pp
21 Feb 202135.1% —

Source: DLD project registry (Mashrooi) — technical inspections · Data through 24 Nov 2026 · percentage as recorded at each inspection; inspections are irregular, and an unchanged value means no new inspection, not that work stopped · Methodology v1.0 ↗

By number of bedrooms

HomesSalesMedian priceMedian AED/sqftMedian sizeMedian rentGross yield
1-bedroom apartments low sample (7) 7AED 750k 1 153 646 sqft — —
2-bedroom apartments low sample (5) 5AED 1.03M 898 1 247 sqft — —

Source: Registered DLD sales and Ejari rental contracts · Data through 24 Nov 2026 · yield shown only where at least 15 rents and 15 ready-home sales support it · Methodology v1.0 ↗

Latest registered sales

DatePropertyRegistrationSizePriceAED/sqft
26 Oct 20262 B/R FlatReady 960 sqftAED 1 030 000 1 073
22 Oct 20262 B/R FlatReady 840 sqftAED 850 000 1 012
2 Jul 20261 B/R FlatReady 646 sqftAED 720 000 1 114
30 Jun 20262 B/R FlatReady 1 256 sqftAED 1 008 678 803
24 Jun 20261 B/R FlatReady 644 sqftAED 745 000 1 157
27 Apr 20261 B/R FlatReady 646 sqftAED 1 300 000 2 014
16 Mar 20262 B/R FlatReady 1 247 sqftAED 1 120 000 898
26 Jan 20261 B/R FlatReady 646 sqftAED 600 000 929
15 Jan 20261 B/R FlatReady 644 sqftAED 750 000 1 165
12 Jan 20262 B/R FlatReady 1 247 sqftAED 1 040 000 834
5 Jan 20261 B/R FlatReady 1 307 sqftAED 1 060 000 811
20 Nov 20251 B/R FlatReady 651 sqftAED 750 000 1 153

Source: Registered DLD transactions · Data through 24 Nov 2026 · individual registrations, shown exactly as recorded, without trimming · Methodology v1.0 ↗

Every registration, on request

The full DLD record for Binghatti Gate: every registered sale, mortgage and gift, and every Ejari rent contract. It loads only when you ask; filter, sort and download it as CSV.

Registered sales by year

05010020182021202220232024202520260501002018202120222023202420252026

registered sales per calendar year; the current year is incomplete

By month

0123AugSepOctNovDecJanFebMarAprMayJunJul0123SepNovJanMarMayJul

registered sales per month, Aug 2024 – Jul 2025

YearSalesMedian priceMedian AED/sqftTotal registered value
202611AED 1.01M 1 012AED 10.22M
202519AED 750k 1 088AED 16.38M
202426AED 730k 1 054AED 20.62M
202329AED 660k 900AED 20.59M
202226AED 522k 763AED 15.02M
2021117AED 531k 740AED 68.31M
20181— —AED 12.74M

Source: Registered DLD transactions · Data through 24 Nov 2026 · calendar years; the current year is partial · Methodology v1.0 ↗

Rent and gross yield by year, 2022–2026

Median annual rent, AED thousand
Year1-bed flat2-bed flatGross yield
2026 YTD 60k85k—
2025 60k90k—
2024 56k85k7.71%
2023 48k75k7.79%
2022 40k60k8.00%

Source: Ejari rental contracts and registered DLD sales · Data through 24 Nov 2026 · median annual rent per year a contract starts, shown from 15 contracts; yield = median rent ÷ median ready-home price of the same year and home type, from 15 of each · Methodology v1.0 ↗

Price and sales, month by month

MonthSalesMedian priceMedian AED/sqftIQR AED/sqft
Jul 20248 AED 720k1 107 1 049 – 1 122
Jun 20241 —— —
May 20244 —— —
Apr 20243 —— —
Mar 20243 —— —
Feb 20240 —— —
Jan 20241 —— —
Dec 20234 —— —
Nov 20234 —— —
Oct 20236 AED 652k895 777 – 945
Sep 20230 —— —
Aug 20231 —— —
Jul 20232 —— —

Source: Registered DLD transactions · Data through 24 Nov 2026 · complete months only; the current month is excluded because DLD keeps registering it · Methodology v1.0 ↗

What these numbers do not show

  • Prices from the developer. Nothing here is a price list, a payment plan or availability — these are transactions already registered with DLD.
  • Whether construction is moving. The completion percentage is the figure recorded at the last technical inspection, and inspections are irregular: an unchanged number does not mean work stopped.
  • A handover promise. The declared completion date is a registry field, not a commitment.
  • A reliable price. Only 12 sales registered in the last 12 months here.
  • Asking prices. Everything here is a registered transaction; what a home was listed at is a different number.
  • Off-market and cash-equivalent deals that never reach the registry, and the price actually negotiated before registration.
  • Service charges, chiller fees, agency commission, DLD transfer fees or mortgage costs — none of them are inside these prices.

Where this project sits

More projects in Jumeirah Village Circle

Questions about Binghatti Gate

Who is the developer of Binghatti Gate?

The Dubai Land Department project registry lists Binghatti Developers Fze as the developer of Binghatti Gate.

Is Binghatti Gate completed?

The DLD registry status of Binghatti Gate is Finished, 100% complete at the last DLD inspection. The declared completion date in the registry is 17 Jan 2022 — a registry date, not a handover promise.

How many homes are in Binghatti Gate?

The DLD registry records 132 units in Binghatti Gate.

What is the price per square foot in Binghatti Gate?

Over the last 12 complete months the median registered sale in Binghatti Gate was AED 929k, or AED 1 043 per sqft, from 12 registered sales. These are DLD registrations, not asking prices.

Who holds the escrow account for Binghatti Gate?

The escrow agent recorded by DLD for Binghatti Gate is Sharjah Islamic Bank.

Where is Binghatti Gate?

Binghatti Gate is in the Jumeirah Village Circle community.

Where does this data come from?

From Dubai Land Department open data — the project registry, unit register and registered sales — rebuilt every night. Data through 24 Nov 2026.

Source: DLD project registry, unit register and registered sales · Data through 24 Nov 2026 · answers built from registry fields · Methodology v1.0 ↗

Cite or reuse this data

Machine-readable mirrors of this page: Markdown · JSON · llms.txt. How to cite: “Binghatti Gate — Data Dubai, Continental Club Property, data through 24 Nov 2026, https://datadubai.ae/projects/binghatti-gate/”. Reuse is permitted with attribution.