Data Dubai

Greenspoint

GreenspointActive43% built196 homesDLD data through 24 Nov 2026

Updated 24 Nov 2026 · latest DLD registrations 24 Nov 2026 · DLD project registry and registered sales · trailing 12 months Nov 2025 – Oct 2026

Ask an AI about Greenspoint: ChatGPT · Claude · Perplexity

Greenspoint is a project by Emaar Dubai South Dwc Llc, recorded at 43% complete at its last Dubai Land Department inspection. Fewer than 5 sales registered here in the last 12 months, so no median is published. Registry facts come from DLD; prices are registered transactions, not asking prices.

Median sale price
—
not enough sales
DLD verified
Median price per sqft
—
built residential only
DLD verified
Registered sales
2 -99.0% y/y
all property types · trailing 12 complete months
DLD verified
Off-plan share
100.0%
of registered sales in the window
DLD verified

Source: Registered DLD transactions · Data through 24 Nov 2026 · sample 2 records · outlier-trimmed median, complete months only · Methodology v1.0 ↗

What the DLD registry says about this project

FieldValue
DeveloperEmaar Dubai South Dwc Llc
StatusActive
Construction progress43% — at the last DLD inspection
Registered with DLD28 Jan 2025
Construction started30 Jan 2025
Declared completion31 Mar 2029 — registry date, not a handover promise
Units in the project196
Project area46 601 sqm
Escrow agentFirst Abu Dhabi Bank P.J.S.C.
Project number3514

Source: DLD project registry (Mashrooi) · Data through 24 Nov 2026 · registry fields as recorded, not developer marketing · Methodology v1.0 ↗

Price per square foot, month by month

1 2501 5001 7502 000Mar 2025May 2025Jul 2025Sep 2025Nov 2025Jan 2026Mar 2026May 2026Jul 20261 2501 5001 7502 000Mar 2025Sep 2025Mar 2026

median   interquartile range (middle 50% of transactions)

Source: Registered DLD transactions · Data through 24 Nov 2026 · monthly medians, months with fewer than 5 registered sales are left blank; the line stops at Aug 2025: in the 14 months since, no month reached the five registered sales a median needs (5 in total) · Methodology v1.0 ↗

Construction, inspection by inspection

The DLD registry holds 6 technical inspections for this project, from 22 Jan 2025 at 0.0% to 21 Jul 2026 at 42.9%. Over the inspections since 22 Jan 2025 it moved 2.40 percentage points a month. Inspections are irregular and the percentage is what was recorded at each one, not a live measure of the site.

0%25%50%75%100%declared 2029-03-312025-01-222026-07-21

each dot is one DLD technical inspection; the line between two of them is drawn, not measured; the dashed mark is the completion date declared in the registry

InspectionRecordedChange
21 Jul 202642.9% +16.6 pp
21 Apr 202626.3% +18.3 pp
25 Nov 20258.0% +0.0 pp
25 Nov 20258.0% +6.6 pp
30 Jul 20251.4% +1.4 pp
22 Jan 20250.0% —

Source: DLD project registry (Mashrooi) — technical inspections · Data through 24 Nov 2026 · percentage as recorded at each inspection; inspections are irregular, and an unchanged value means no new inspection, not that work stopped · Methodology v1.0 ↗

By number of bedrooms

HomesSalesMedian priceMedian AED/sqftMedian sizeMedian rentGross yield
3-bedroom apartments insufficient data 1— — — — —
4-bedroom apartments insufficient data 1— — — — —

Source: Registered DLD sales and Ejari rental contracts · Data through 24 Nov 2026 · yield shown only where at least 15 rents and 15 ready-home sales support it · Methodology v1.0 ↗

Latest registered sales

DatePropertyRegistrationSizePriceAED/sqft
2 Nov 20263 B/R VillaOff-plan 2 085 sqftAED 3 438 888 1 650
10 Jun 20263 B/R VillaOff-plan 1 869 sqftAED 3 363 888 1 799
17 Nov 20254 B/R VillaOff-plan 5 436 sqftAED 4 159 010 765

Source: Registered DLD transactions · Data through 24 Nov 2026 · individual registrations, shown exactly as recorded, without trimming · Methodology v1.0 ↗

Every registration, on request

The full DLD record for Greenspoint: every registered sale, mortgage and gift. It loads only when you ask; filter, sort and download it as CSV.

Registered sales by year

010020020252026010020020252026

registered sales per calendar year; the current year is incomplete

By month

012SepOctNovDecJanFebMarAprMayJunJulAug012OctDecFebAprJunAug

registered sales per month, Sep 2025 – Aug 2026

YearSalesMedian priceMedian AED/sqftTotal registered value
20261— —AED 3.36M
2025196AED 3.80M 1 584AED 750.81M

Source: Registered DLD transactions · Data through 24 Nov 2026 · calendar years; the current year is partial · Methodology v1.0 ↗

Price and sales, month by month

MonthSalesMedian priceMedian AED/sqftIQR AED/sqft
Aug 20258 AED 3.65M1 908 1 896 – 1 958
Jul 202533 AED 3.62M1 917 1 896 – 1 951
Jun 202523 AED 3.67M1 901 1 577 – 1 967
May 202512 AED 3.72M1 819 1 311 – 1 902
Apr 202546 AED 3.96M1 403 1 241 – 1 489
Mar 202570 AED 3.96M1 457 1 235 – 1 811

Source: Registered DLD transactions · Data through 24 Nov 2026 · complete months only; the current month is excluded because DLD keeps registering it · Methodology v1.0 ↗

What these numbers do not show

  • Prices from the developer. Nothing here is a price list, a payment plan or availability — these are transactions already registered with DLD.
  • Whether construction is moving. The completion percentage is the figure recorded at the last technical inspection, and inspections are irregular: an unchanged number does not mean work stopped.
  • A handover promise. The declared completion date is a registry field, not a commitment.
  • A reliable price. Only 2 sales registered in the last 12 months here.
  • Asking prices. Everything here is a registered transaction; what a home was listed at is a different number.
  • Off-market and cash-equivalent deals that never reach the registry, and the price actually negotiated before registration.
  • Service charges, chiller fees, agency commission, DLD transfer fees or mortgage costs — none of them are inside these prices.

Where this project sits

More projects in Dubai World Central

Questions about Greenspoint

Who is the developer of Greenspoint?

The Dubai Land Department project registry lists Emaar Dubai South Dwc Llc as the developer of Greenspoint.

Is Greenspoint completed?

The DLD registry status of Greenspoint is Active, 43% complete at the last DLD inspection. The declared completion date in the registry is 31 Mar 2029 — a registry date, not a handover promise.

How many homes are in Greenspoint?

The DLD registry records 196 units in Greenspoint.

What is the price per square foot in Greenspoint?

Too few sales were registered in Greenspoint in the last 12 months to publish a median; earlier registered sales are shown in the charts on this page.

Who holds the escrow account for Greenspoint?

The escrow agent recorded by DLD for Greenspoint is First Abu Dhabi Bank P.J.S.C..

Where is Greenspoint?

Greenspoint is in the Dubai World Central community.

Where does this data come from?

From Dubai Land Department open data — the project registry, unit register and registered sales — rebuilt every night. Data through 24 Nov 2026.

Source: DLD project registry, unit register and registered sales · Data through 24 Nov 2026 · answers built from registry fields · Methodology v1.0 ↗

Cite or reuse this data

Machine-readable mirrors of this page: Markdown · JSON · llms.txt. How to cite: “Greenspoint — Data Dubai, Continental Club Property, data through 24 Nov 2026, https://datadubai.ae/projects/greenspoint/”. Reuse is permitted with attribution.